Connection price list as of 1.6.2026
The connection price list shows the connection charges collected for joining the Turku Energia Sähköverkot Oy's electricity network.
When connecting to a low-voltage electricity distribution network, the connection charge is determined by the price zone in accordance with the location of the connection. The connection point is generally at the site boundary closest to the feeding direction.
The maximum available low-voltage connection size is 3x1000A.
This price list shall apply to the connection of both metering points and electricity plants to the electricity grid.
Low-voltage connection charges: Zone A
| Connection main fuse, phase x A | Connection charge €, VAT 0 | Connection charge €, VAT 25,5 % |
|---|---|---|
| (1 x 25 | 1 286,25 | 1 614,24) |
| 3 x 25 | 1 645,00 | 2 064,48 |
| 3 x 35 | 1 995,00 | 2 503,73 |
| 3 x 50 | 2 520,00 | 3 162,60 |
| 3 x 63 | 2 975,00 | 3 490,16 |
| 3 x 80 | 3 570,00 | 4 480,35 |
| 3 x 100 | 4 270,00 | 5 358,85 |
| 3 x 125 | 5 145,00 | 6 456,98 |
| 3 x 160 | 6 370,00 | 7 994,35 |
| 3 x 200 | 7 770,00 | 9 751,35 |
| 3 x 250 | 9 520,00 | 11 947,60 |
| 3 x 315 | 11 795,00 | 14 802,73 |
| yli 3 x 315 | 770,00 € + 35,00 €/A | 966,35 € + 43,93 €/A |
Low-voltage connection charges: Street and general area zone
| Connection main fuse, phase x A | Connection charge €, VAT 0 | Connection charge €, VAT 25,5 % |
|---|---|---|
| (1 x 25 | 3 596,25 | 4 513,29) |
| 3 x 25 | 3 955,00 | 4 963,53 |
| 3 x 35 | 4 305,00 | 5 402,78 |
| 3 x 50 | 4 830,00 | 6 061,65 |
| 3 x 63 | 5 285,00 | 6 632,68 |
| yli 3 x 63 | 3 080,00 € + 35,00 €/A | 3 865,40 € + 43,93 €/A |
Low-voltage connection charges: Small production connections up to 2 MVA (No consumption)
| Connection main fuse, phase x A | Connection charge €, VAT 0 | Connection charge €, VAT 25,5 % |
|---|---|---|
| 3 x 25 | 770,00 | 966,35 |
| 3 x 35 | 770,00 | 966,35 |
| 3 x 50 | 770,00 | 966,35 |
| 3 x 63 | 770,00 | 966,35 |
| 3 x 63 – 3 x 1000 | 770,00 | 966,35 |
Details of low-voltage connections
The connection charge affords the connecting party rights under the Connection Agreement.
Currently valid VAT is charged for the connection charge. The connection charges are non-refundable. The connection is transferable to the new owner in accordance with the connection terms.
Connecting to medium voltage network (10 / 20 kV)
When connecting to a medium voltage network (10 / 20 kV), the connection fee is based on the size of the connection (kVA).
When connecting to the medium voltage network, the delivery time is determined on a case-by-case basis.
In the medium voltage network, the actual connection charge is the capacity reservation fee of € 30/ kVA (VAT 0) in 10 kV network and € 23/ kVA (VAT 0) in 20 kV network. When connecting to a substation (10 kV and 20 kV), there is a capacity reservation charge of EUR 19/kVA (VAT 0).
For the connection of production in the 10 kV medium voltage network, the direct costs of the network expansion due to the connection are charged from up to 2 MVA plants as the actual connection charge, and from over 2 MVA plants a capacity reservation charge of € 15.00/ kVA (VAT 0), as well as the direct network expansion costs arising from the connection separately.
For the connection of production in the 20 kV medium voltage network, the direct costs of the network expansion due to the connection are charged from up to 2 MVA plants as the actual connection charge, and from over 2 MVA plants a capacity reservation charge of € 11.50/ kVA (VAT 0), as well as the direct network expansion costs arising from the connection separately.
Connection to high voltage network
When connecting to the high-voltage network, the delivery time is determined on a case-by-case basis.
As an actual connection charge, a capacity reservation fee of € 11,530 / MVA (VAT 0) and possible network expansion costs are charged for the connection.
The connection of production to a high-voltage network is subject to a connection charge, collected based on a capacity reservation that takes into account the benefits obtained from the production by the network, which is € 2306/MVA (VAT 0) and possible network expansion costs.
When connecting through circular high voltage network, the cables of the area network remain in the ownership of Turku Energia Sähköverkot Oy. The connection point is then in the switchgear owned by the connecting party. In the case of a radial network connection, the connection point and the ownership limit of the cables must be agreed separately.
Changing and maintaining the connection
If the size of the connection is subsequently increased, an additional connection charge is charged, which is in zones A and "Street and public area" the difference between the connection charge for the new connection size and the connection charge for the previous connection size according to the valid price list.
Temporary connection
A fixed-term Connection Agreement allows a temporary electricity metering point to be connected to the electricity distribution network without a connection charge.
A temporary connection (e.g. a work site) can be supplied with a temporary electricity product in accordance with the Network Service Price List for a maximum of two (in special cases a maximum of five) years.
Connection of production to the electricity grid
The connection charges for electricity plants above 2 MVA and up to 2 MVA shall be determined in accordance with the decision of the Energy Authority.
Connection Criteria
The Connection Agreement prepared on the connection shall be subject to the conditions of connection for electricity metering points confirmed by the Energy Authority and in force at any given time, unless otherwise agreed in the Connection Agreement.