Service charges as of 1 May 2021
The service price list shows the service charges related to Turku Energia Sähköverkot Oy's power transmission. Other services are charged as per agreement with the customer.
Connection charges for the initiation of power transmission
Requiring that the safety of the connection has been verified by 15.00. If the safety of the connection is reported later, the connection of power will be postponed to the following working day.
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Connection on the following day, ordered on a working day | free of charge | free of charge |
Connection on the same day | 50,00 | 62,00 |
Invoice and document charges
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Extra invoice requested by the customer outside the normal billing period | 7,50 | 9,30 |
Document charge (certificates, copies of invoices, etc.) | 7,50 | 9,30 |
Hourly document charge (€/h) | 52,50 | 65,10 |
Meter examinations
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Examination of a meter made at the location of use at the customer's request, and the meter turns out, upon inspection, to be in working order | 60,00 | 74,40 |
Examination of a meter made at the service provider's location at the customer's request, and the meter turns out, upon inspection, to be in working order | 200,00 | 248,0 |
Electrician’s visit
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Electrician’s unsuccessful visit, the electrician is unable to perform the task for reasons stemming from the customer | 40,00 | 49,60 |
Energy advice
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Home visit by an energy advisor | 40,00 | 49,60 |
Delay of payment
Service | €, VAT 0 % | €, VAT 24 % |
---|---|---|
Disconnection of power | 50,00 | |
Disconnection of power (service charge for electricity provider) | 50,00 | 62,00 |
Reconnection on the same weekday (Mon-Fri). Reconnection requires that the payment is made and an appointment for reconnection is made before 12:00 noon. In other cases the connection is made on the following weekday. | 50,00 | 62,00 |
Collection visit | 50,00 | 62,00 |
Payment reminders and other payment requests as well as disconnection notices are dealt by Ropo Capital with Turku Energia’s mandate. Payment reminder sendings are charged according to the Debt Collection Act. Ropo Capital will charge additional fees for other collection operations according to their current price list.
Prices valid until further notice.